Step 1: Position the Enphase Q Cable

A. Plan each cable segment to allow drop connectors on the Enphase Q Cable to align with
each PV module. Allow extra length for slack, cable turns, and any obstructions.
B. Mark the approximate centers of each PV module on the PV racking.
C. Lay out the cabling along the installed racking for the AC branch circuit.
D. Cut each segment of cable to meet your planned needs.
WARNING: When transitioning between rows, secure the cable to the rail to prevent cable
damage or connector damage. Do not count on connector to withstand tension.

Step 2: Position the Q Aggregator or Junction Box

A. Verify that AC voltage at the site is within range.
B. Install an Enphase Q Aggregator or junction box at a suitable location on the racking. See the
Enphase Q Aggregator Quick Install Guide.
C. Provide an AC connection from the Enphase Branch Aggregator back to the electricity
network using equipment and practices as required by local jurisdictions.
15
Service Type and Voltage: L1-L2
240 V Split-Phase
208 V Single-Phase
© 2017 Enphase Energy Inc. All rights reserved.
IQ 6 / IQ 6+ Micro Installation and Operation
211 to 264 VAC
183 to 229 VAC