(Adjustment)
1.
Place the reels in the L size position.
2.
Push the iron core of M-Stopper Solenoid by
hand.
3.
Observe the clearance (A) between Mech.
Chassis and M-Stopper as shown in Figure
2-30-2. And make sure that it is within 1.1 to
1.3mm.
4.
If not, loosen the 2 screws (A) as shown in Figure
2-30-1, which fixed M-Stopper Solenoid. And
adjust the position of M-Stopper Solenoid so that
the clearance (A) is within the specification. And
tighten the 2 screws (A) as shown in Figure
2-30-2.
Figure 2-30-2
2-31. T4 Post Position Adjustment
1.
Confirm that the hole (B) of T4 connection Gear
match with the hole of T4 post as shown in figure
2-31.
2.
Confirm that the portion (C) of T4 connection
Gear and hole (A). Those are located as shown in
figure 2-31.
3.
If not, adjust the phase of T4 post following the
above procedure.
Note:
This
confirmation
unloading condition.
MECH-57
should
be
performed
Figure 2-31
on