Commissioning - Start Up Checklist - Ametek Drexelbrook Universal IV Quick Start Manual

Cut monitor model transmitters 2-wire rf admittance / capacitance level measurement system with hart protocol
Table of Contents

Advertisement

Universal IV - Level Measurement System
1.4

Commissioning - Start Up Checklist

DO NOT connect power until you have gone through the
checklist below
• Are the wetted components resistant to the corrosive
properties of the tank product?
• Does the information given on the nameplate correspond
with the application?
• Ex d applications: Have you connected the equipotential
bonding system correctly?
• Ex i applicatons: Are you using intrinsic barrier within
the correct parameters?
• Did you install cable entries of the correct internal
diameter so there is a good seal around the cable?
• Are the cable glands suitably certified per the
application and the hazardous area parameters?
• Do not use the earth terminal in the wiring
compartment; use the equipotential bonding system.