9. Repeat all of these steps to install additional 2145 UPS-1Us.
Installing the 2145 UPS-1U cable retention bracket
The 2145 UPS-1U cable retention bracket ensures that the power cable connection
between the 2145 UPS-1U and the SAN Volume Controller 2145-8G4 or the SAN
Volume Controller 2145-8F4 is stable.
Install the bracket after you have installed the power cable between the 2145
UPS-1U and the SAN Volume Controller 2145-8G4 or the SAN Volume Controller
2145-8F4 node.
You can attach the bracket by performing the following steps:
1. Install the power cable into the rightmost power supply on the rear of the 2145
2. Remove the bracket and the two screws (shown in Figure 58) from the
Figure 58. 2145 UPS-1U power cable retention bracket hardware
3. Place the bracket over the power supply inlets on the right rear of the 2145
4. Position the bracket with the power cable protruding through the rightmost slot
5. Secure the bracket in place with one screw on each side, as shown in Figure 59
86
IBM System Storage SAN Volume Controller: Hardware Installation Guide
it persists for more than five minutes after a SAN Volume Controller has been
connected to this 2145 UPS-1U and powered on.
UPS-1U.
packaging.
UPS-1U, so that the two screw holes line up.
in the bracket.
on page 87.