Installing the 2145 UPS-1U

|
|
|
|
|
|
|
80
IBM System Storage SAN Volume Controller: Hardware Installation Guide
8. Install and verify the master console, unless it is already installed. Optionally,
you can perform this step first.
After you finish these steps, the hardware installation is complete.
Before you can use the SAN Volume Controller, you need to install the
uninterruptible power supply (UPS).
Complete the following steps to install the 2145 UPS-1U:
1. Install the support rails for the 2145 UPS-1U.
2. Install the 2145 UPS-1U into the rack.
3. Connect the 2145 UPS-1U battery.
4. Connect the power cables to the 2145 UPS-1U.
5. Install the 2145 UPS-1U cable retention bracket.
Installing the support rails for the 2145 UPS-1U
You must install the support rails in the rack before installing the 2145
uninterruptible power supply-1U (2145 UPS-1U).
Complete the following prerequisites before installing the support rails:
1. Use the user's hardware location chart to determine where in the rack that the
2145 UPS-1U is to be installed.
2. At the back of the rack, observe the Electronic Industries Alliance (EIA)
positions and determine where you are going to install the 2145 UPS-1U.
Because of its weight, position the 2145 UPS-1U where it is easy to handle in
one of the lower positions in the rack.
Perform the following steps to install the support rails for the 2145 UPS-1U:
1. Open the top of the 2145 UPS-1U shipping carton. Grip the flaps on either
side of the 2145 UPS-1U.
2. Lift the 2145 UPS-1U clear of the shipping carton and place it on a flat, stable
surface with the front facing you.
3. Attach the long side of a mounting bracket
UPS-1U using four M3 × 6 screws
Figure 49. Installing the support rails for a 2145 UPS-1U into the rack
4. Loosen the assembly wing nuts (
assemblies and adjust the rail size to the depth of your rack.
1
to each side of the 2145
2
for each bracket, as shown in Figure 49.
1
1
in Figure 50 on page 81) on both rail
2