Installation
5. Allow the grout to set.
1. Baseplate
2. Shims or wedges
3. Grout
4. Foundation
5. Sleeve
6. Dam
7. Bolt
Figure 18: Pour grout into baseplate
6. Fill the remainder of the baseplate with grout, and allow the grout to set for at least 48
hours.
1. Baseplate
2. Grout
3. Foundation
4. Dam
5. Bolt
Figure 19: Fill remainder of baseplate with grout
7. Remove the leveling jackscrews after the grout hardens in order to remove any stress
points.
8. Tighten the foundation bolts.
30
Model 3700, API Type OH2 / ISO 13709 1st and 2nd Ed. / API 610 8/9/10/11th Ed. Installation, Operation, and Maintenance
Manual