Putting in operation for the first time (for specialized personnel only)

Version 1.3_15 EN
To get a complete overview of the operation of the high-voltage
power supply unit you should read the instructions concerning
the operation of the filament power supply (FPS) in connection
with the electron beam vaporizer described in the Appendix
The equipment may only be put in operation by trained
specialized personnel.
The high-voltage power supply unit is put in operation together
with the whole system.
The components of the complete system
-
High voltage power supply HVP
-
Control unit Genius
-
Filament power supply FPS
-
Vacuum system
-
Electron beam evaporator
must be completely installed and connected before the system is
first put in operation.
To put the system in operation carry out the following tests:
1. Check
-
the earthing connections,
-
the mains supply,
-
the control lines,
-
the high voltage cable
for correct and tight connection.
2. Test the safety circuit (see chapter Fehler! Verweisquelle
konnte nicht gefunden werden., Interlock-connector X304).
3. Test the emergency switch system
NOTICE