G u id e Form S pecification s
5.
The trip units shall include the fol lowing metering func
tions, which shall be displayed on the LCD
a . Current, rms (A of kA). each phase, ± 2.5% accu racy.
b. OPTIONAL: Note: If any of the following are included,
all will be included.
1) Voltage, rms, (V). line-to-line or li ne-to-neutral,
±1.5% accuracy.
2) Energy ( kWh, MWh, GWhl total, ±4% accu racy,
user resettable.
3) Demand (kWh, MWH, GWhl over an adj usta ble
time period of 5 to 60 minutes, ±4% a ccuracy.
4) Peak demand (kW, MW). ± 4% accuracy, user
resettable.
51 Real power ( kW, MW). line-to-line, li ne-to-neutral .
±4% accuracy.
6) Total (apparent) power (kVA, MVA). l i ne-to-li ne, line
to-neutral. ±4% accuracy.
6.
OPTIONAL:
The trip unit shall include all of the following p rotec
tive functions. However, it shall be possible to d isable,
by user-progra m ming, a ny combination of unwa nted
protective functions.
a. U ndervoltage, adj ustable pickup - 50 to 90%, adjust
able delay - 1 to 15 seconds.
b. Overvoltage, adjustable pickup - 1 10 to 150%, adjust
able delay - 1 to 15 seconds.
c. Voltage unbala nce, adjustable pickup - 10 to 5 0%,
adjustable delay - 1 to 1 5 seconds.
d. Current unba lance, adjusta ble pickup - 10 to 50%,
adjusta ble delay - 1 to 1 5 seconds.
e. Reverse power, selectable direction, adjustable
pickup-10kW to 990 kW, adjustable delay - 1 to 15
seconds.
7.
OPTIONAL: The trip unit shall include com m unication
capability as follows:
a. The trip unit through ded icated secondary terminal on
the breaker shall provide a commun ication port for
communication with and access to a remote comput
er via the breaker supplier's standard communication
network and protocol.
b. All metering, setpoints, protective trip co unts and
other event signaling shall be retrieva ble by the re
mote computer.
*With optional Target Module
8.
Current sensors shall be mounted on the breaker fra me
and shall use encapsulated construction to protect
against damage and moisture. ( For g rou nd-fault pro
tection of a four-wire power system, a fourth-neutral
current- sensor shall be mounted in the cable compart
ment, and shall be com patible with the phase overcur
rent sensors.)
9.
The trip unit's LCD and programming functions shall be
operable at all times, even when the breaker is either
open or closed under a no-load condition. M etering
functions, other than cu rrent, protective relaying and
commun ication functions may req u ire a separate power
su pply within the equipment lineup. The external power
supply shall meet the breaker suppl ier's standard rec
ommendations for this type of application.
1 1 1