Casters And Leveling Feet - Vertiv DCE E42611 User Manual

Table of Contents

Advertisement

ITEM
DESCRIPTION
6
Cable pass-through cover
7
Right-side half of bottom cover
8
M6 Flat-head screw (3 per bottom)
9
Front of unit

3.11 Casters and Leveling Feet

CAUTION: When installing the casters and adjusting leveling feet, observe the following safety
precautions:
To install casters, several people are required to tip the rack onto its side. The rack can be very
heavy. Practice safe lifting techniques.
DO NOT lay the rack on its front or back, this may damage the door hinges.
Before tipping, remove the side panels to prevent damage to the locks and latches.
Removing doors and sides helps reduce the weight of the rack.
To field-install casters
1.
Tip the rack over and lay it on its side.
NOTE: Be sure to install swivel casters on the front and fixed casters on the rear of the rack.
2. Install the swivel casters on the front of the rack as shown in the following figure.
The longer side of the caster assembly features 2 holes.
Align the holes over the M8 pem studs located on the side of the frame.
Using a 13-mm socket, secure with M8 keps nut and tighten to 18 ft-lb.
3. The flange of the caster assembly aligns with a hole on the side of the frame. Secure with a M6
carriage bolt and nut and tighten to 7.5 ft-lb.
4. The shorter side of the caster assembly aligns with a hole on the front of the frame. Secure with
a M8 Bolt and tighten to 18 ft-lb.