5. PRE POWER AND CHECKOUT

This Section contains the pre-power and checkout procedure for the SSPB model
SSPBMg-C200-BRE.
WARNING! The information presented in this Section is addressed to the technicians who
have specific training in, and knowledge of the Microwave Power Transmitters.
Inappropriate use of an SSPB may cause serious injury to the operator or damage to the
equipment. Do not attempt to operate an SSPB before becoming thoroughly familiar with
the contents outlined in this Section.

5.1 PRE-POWER PROCEDURES

Before applying prime power to the SSPB, verify that the following conditions are met:
• The voltages of the station AC prime power matches those marked on the ID label; it is
110/220 V AC, 47-63 Hz, single phase, for these units.
• The prime power station is properly grounded.
• All connections are tight, no wires are pinched, and no other hardware has loosened while
handling the SSPB.
• The main power switch on the prime power station is turned OFF.
• The RF input and RF output ports are connected to a matched source and a proper load
capable to withstand full CW RF power see TABLE 1 at (page 13).
• The heatsink is not obstructed.
The cooling fans are not obstructed.
CAUTION!
Failure to verify these pre-power conditions may damage the SSPB causing it
to malfunction. Operating the SSPB before verifying the above conditions may void the
warranty.