Commissioning, inspection, maintenance
Further details regarding the individual steps
Setting the time and date
Press the following keys:
1. |/~ for the required time.
2. d
to confirm.
Configuring the supply system
At the factory, the supply system is set up to discharge from the pellet hopper only.
Press the following keys:
1. |/~ for "Configuration? Yes".
2. d
to confirm.
3. |/~ for the required supply sys-
tem.
Commissioning the supply system
Press the following keys:
1. d
to confirm "Commissioning
Supply system".
2. |/~ for fuel supply "Enable?
Yes".
The display shows "Fuel
supply enabled".
3. g
approx. 60 s after the first pel-
lets trickle into the combus-
tion chamber.
After successful commissioning, the dis-
play shows "Commissioning fin-
ished".
12
3. |/~ for the required date.
4. d
to confirm.
The display shows "Config-
uration Supply system".
4. d
to confirm.
The display shows "Already
set". The display shows
"Commissioning Supply
system".
For an overview of possible supply sys-
tems, see page 62.
Now the combustion grate is cleaned to
move the remaining pellets into the ash
container.
The display will show the following in
sequence "Please wait", "Grate clean-
ing" and "Empty ash box".
Now empty the ash container to remove
unburned pellets (see page 50).
Heating mode starts automatically as
soon as there is a heat demand.
Note
Now a consumer actuator test should
be carried out (see page 39), even if
heating mode has been started.