CHAPTER 5: SETTINGS
If no trigger is assigned in the
calculation method 2. If a trigger is assigned, the maximum allowed time between two trigger signals is 60
NOTE
minutes. If no trigger signal appears within 60 minutes, demand calculations are performed and available, and
the algorithm resets and starts the new cycle of calculations. The minimum required time for trigger contact
closure is 20 ms.
5.3.10.4 Calculation method 3: Rolling demand
This method calculates a linear average of the quantity (RMS current, real power, reactive power, or apparent power) over
the programmed demand time interval, in the same way as Block Interval. The value is updated every minute and
indicates the demand over the time interval just preceding the time of update.

5.3.11 User-programmable LEDs

5.3.11.1 Menu
SETTINGS  PRODUCT SETUP  USER-PROGRAMMABLE LEDS
 USER-PROGRAMMABLE
 LEDS
The 48 amber LEDs on relay panels 2 and 3 can be customized to illuminate when a selected FlexLogic operand is in the
logic 1 state. The trip and alarm LEDs on panel 1 can also be customized in a similar manner. To ensure correct
functionality of all LEDs, an LED test feature is also provided.
5.3.11.2 LED test
SETTINGS  PRODUCT SETUP  USER-PROGRAMMABLE LEDS  LED TEST
 LED TEST
When enabled, the LED test can be initiated from any digital input or user-programmable condition, such as a user-
programmable pushbutton. The control operand is configured under the
LEDs, including the LEDs of the optional user-programmable pushbuttons.
The test consists of the following three stages:
1.
All 62 LEDs on the relay are illuminated. This is a quick test to verify if any of the LEDs is "burned." This stage lasts as
long as the control input is on, up to a maximum of 1 minute. After 1 minute, the test ends.
2.
All the LEDs are turned off, and then one LED at a time turns on for 1 second, then back off. The test routine starts at
the top left panel, moving from the top to bottom of each LED column. This test checks for hardware failures that lead
to more than one LED being turned on from a single logic point. This stage can be interrupted at any time.
3.
All the LEDs are turned on. One LED at a time turns off for 1 second, then back on. The test routine starts at the top left
panel moving from top to bottom of each column of the LEDs. This test checks for hardware failures that lead to more
than one LED being turned off from a single logic point. This stage can be interrupted at any time.
C60 BREAKER PROTECTION SYSTEM – INSTRUCTION MANUAL
setting and the
DEMAND TRIGGER
 LED TEST
 TRIP & ALARM LEDS
 USER-PROGRAMMABLE
 LED 1
 USER-PROGRAMMABLE
 LED 48
LED TEST FUNCTION:
Disabled
LED TEST CONTROL:
Off
is "Block Interval," use
CRNT DEMAND METHOD
See below
See page 5-95
See page 5-95
Range: Disabled, Enabled
Range: FlexLogic operand
setting. The test covers all
LED TEST CONTROL
PRODUCT SETUP
5
5-93