Connecting The Condensate Discharge Pipe; Gas Connection - DeDietrich C 330 ECO Installation, User And Service Manual

Gas fired floor-standing condensing boiler
Hide thumbs Also See for C 330 ECO:
Table of Contents

Advertisement

4. Installation
2
6
4.5

Gas connection

30
The flow pipe is fitted with the following components:
1
1
3
4
2
3
5
4
5
6
T003476-C
4.4.3.
Discharge the condensed water directly into the drain using a
syphon. In view of the acidity level (pH 2 to 5), only use plastic material
for the discharge pipe.
1. Install a plastic drain pipe on the syphon (dia. 32 mm or larger,
connected to a drain).
CAUTION
4
4
4
4
Tube pocket for a temperature sensor for an external
control ( ½" ).
Vent device (⅛").
Connection for safety valve (1½").
Pressure gauge (½").
Flow sensor (M6).
High-limit thermostat (M4).

Connecting the condensate discharge pipe

For the connection(s) of the boiler C 630 ECO: The
features and instructions described are for each boiler
module.
Do not make a fixed connection in order to prevent an
overpressure in the siphon.
The condensate drain must be connected openly to
the drain.
Set the discharge pipe at a gradient of at least 5 -
10 mm per metre, maximum horizontal length 5
metres.
Do not drain condensation water into a roof gutter at
any time.
Connect the condensate discharge pipe in
accordance with prevailing standards.
For the connection(s) of the boiler C 630: The features and
instructions described are for each boiler module.
C 330 ECO - C 630 ECO
31/05/2012 - 7600532-01