Power Connections

Once all hard drives have been properly installed and the I/O ports or management
interfaces have been connected, the system can be powered on.

Checklist

BEFORE powering on the system, please check the following:
 Hard drives: Hard drives are correctly installed in the drive trays.
 Drive trays: All the drive trays, whether or not they contain a hard drive,
have been installed into the system.
 Cable connections: The system has been correctly connected to host
computer(s), management computers, or external networking devices.
 Ambient temperature: Make sure the surrounding environment
temperature is not higher 35 degrees Celsius (with CBM).
NOTE
Make sure you use the power cables provided that are at least 1.2 meters in length.
DO NOT use extension cables as the power cables are designed to connect ONLY
and DIRECTLY to relocatable power taps (RPTs) on server cabinets.