Startup And Operation; General; Figure 3-1. Integral Electronics - Emerson Oxymitter 5000 Instruction Manual

Oxygen transmitter with foundation fieldbus communications
Hide thumbs Also See for Oxymitter 5000:
Table of Contents

Advertisement

Oxymitter 5000
Install all protective equipment covers
and safety ground leads before
equipment startup. Failure to install
covers and ground leads could result
in serious injury or death.
NOTE
Refer to Appendices A, B, and C for
fieldbus information concerning the
Oxymitter 5000.
3-1

GENERAL

a. Verify Mechanical Installation
Ensure the Oxymitter 5000 is installed cor-
rectly (Section 2, INSTALLATION).
b. Verify Terminal Block Wiring
1. Remove screw (36, Figure 4-1), gasket
(37), and cover lock (38) that secure
Rosemount Analytical Inc.
A Division of Emerson Process Management
SECTION 3

STARTUP AND OPERATION

Figure 3-1. Integral Electronics

Instruction Manual
IB-106-350 Rev. 1.2
the terminal block cover. Remove the
cover to expose the terminal block
(Figure 3-1).
2. Check the terminal block wiring. Be
sure the power, fieldbus signal, and
logic outputs are properly connected
and secure.
3. Install the housing cover on the termi-
nal block and secure with cover lock
(38, Figure 4-1), gasket (37), and
screw (36).
4. For an Oxymitter 5000 with an inte-
grally mounted SPS 4000, remove
screws (26, Figure 4-11) and terminal
cover (27). Check that the power and
signal terminations are properly con-
nected to terminal strip (25) and secure
according to instructions in Section 2,
INSTALLATION.
5. Install terminal cover (27) and secure
with screws (26).
Startup and Operation
April 2001
3
3-1

Advertisement

Table of Contents
loading

Table of Contents