Motor installation
• Grease the drive shaft and ensure that the key is well positioned.
• Insert the motor and fix it by means of the 4 screws and 4 grower
provided (fig. 15), properly greased.
• Connect the faston connectors by re-
specting the polarity (fig. 16).
System check and mechanic adjustment
Follow the sequence described below to verify the opening
of the hatch:
• The BTR propeller should be disconnected from power.
• Take the ring off and remove the pin (fig. 17 / part. A), unhook the
actuator from the lever (part B), ensuring that the system is free
to open and close without any mechanical hindrance.
WARNING: when the actuator is manually unhooked, the
thruster completely comes out due to its weight, therefore
ensure that nobody stands in its range of action.
• Fig. 18 - Thread one end of the cable through the lid's bracket (part A). And then below the guide fixed onto the tunnel (part. B).
Hook the end of the cable to the two springs which are already fitted onto the moving body) (part. C).
Final installation of the cable in the lid (part. D).
Fig. 18
B
CABLE GUIDE
STEEL
CABLE
RETRACTABLE THRUSTER BTR250 - IT EN - REV08B
Fig. 16
CABLE N°7
A
STEEL CABLE
C
TUNNEL
INSTALLATION
Fig. 15
CABLE N°7
CABLE N°6
CABLE N°5
Fig. 17
A
D
SPRINGS
EN
B
27