Nabco GT1175 Quick Setup Manual page 17

Hurricane slide door system
Hide thumbs Also See for GT1175:
Table of Contents

Advertisement

www.NabcoEntrances.com
Rev 8-10-16
3. Ensure the Leading Edge of the Slide door and (other Slide door or Jamb Tube) are parallel.
4. Ensure the Leading Edge of the Slide door and Header are parallel.
5. Retighten the 7/16-20 Whizlock nuts. Do not overtighten.
Parallel Gap
DN 0895
6 .7 Anti-Rise Rollers
CAUTION
1. Fully close Slide Door. Ensure each Anti-Rise Bracket is aligned directly above each Anti-Rise Roller. If not, go to the Anti-Rise
Bracket and loosen (1) 3/8-16 Whizlock Nut with a 9/16 inch wrench.
2. Slide the Anti-Rise Bracket to the left or right. Retighten screws. Do not overtighten.
An -Rise Roller
DN 0929
3. Loosen (2) Anti-Rise Rollers located towards the middle of the Carrier. Turn the Axle clockwise until there is a 1/64 inch to
1/32 inch gap between the Roller Wheel and the Top Track.
a. Gap should be about the same thickness of a credit card.
4. Retighten the 7/16-20 Whizlock nuts. Do not overtighten.
DN 0898
Parallel Gap
BI PART
Ensure (1) Anti-Rise Bracket is aligned directly above each Anti-Rise Roller.
3/8"-16 Whizlock Nut
An -Rise Bracket
Top of Track
An -Rise
Roller Wheel
GT1175 (H105 Medium) Hurricane Quick Set-Up and Parts Guide
11/16" (17mm) to
15/16" (24mm);
7/8" (22mm)
nominal
3/8"-16 Whizlock Nut
Figure 30 Align Anti-Rise Brackets to Anti-Rise Rollers
An -Rise Roller
An -Rise Bracket
Figure 31 Anti-Rise Roller Wheel and Top Track Clearance
P/N C-00106
Parallel Gap
Figure 29 Floor Gap
SINGLE
1/64 inch to
1/32 inch
clearance
17 of 53