The cabinet can be surface mounted or semi-flush mounted. The door is removable during the
installation period by opening and lifting it off the hinges. The cabinet mounts using two key slots
at the top of the backbox and two additional securing holes located at the bottom.
Carefully unpack the system and check for shipping damage. Mount the cabinet in a clean, dry,
vibration-free area where extreme temperatures or levels of humidity are not encountered. The area
should be readily accessible with sufficient room to easily install and maintain the panel. Locate the
top of the cabinet approximately 5 feet (1.5 m) above the floor with the hinge mounting on the left.
Determine the number of conductors required for the devices to be installed. Sufficient knockouts
are provided for wiring convenience. Select the appropriate knockout(s) and pull the conductors
into the box. All wiring should be in accordance with the National and/or Local codes for fire alarm
systems.

2.1 Backbox Mounting

CAUTION:
!
THE CIRCUIT BOARD CONTAINS STATIC-SENSITIVE COMPONENTS. ALWAYS GROUND
YOURSELF WITH A PROPER WRIST STRAP BEFORE HANDLING ANY BOARDS SO THAT
STATIC CHARGES ARE REMOVED FROM THE BODY. USE STATIC SUPPRESSIVE PACKAG-
ING TO PROTECT ELECTRONIC ASSEMBLIES.
To prevent damage to the circuit board and to facilitate backbox mounting, the chassis with main
circuit board and power supply can be easily removed. Loosen the two 3/8" nuts securing the top
flanges of the chassis, then slide the chassis up to free it from the lower tabs. Place the chassis
assembly in a protective antistatic bag in a safe location until it can be reinstalled in the backbox.
1.
Mark and predrill hole in the wall for the center top keyhole mounting bolt using the dimen-
sions illustrated in Figure 2.2 on page 21.
2.
Install center top fastener in the wall with the screw head protruding.
3.
Place backbox over the top screw, level and secure
4.
Mark and drill the left and right upper and lower mounting holes.
Note: outer holes (closest to sidewall) are used for 16" on-center stud mounting.
5.
Install remaining fasteners and tighten.
grounding stud:
attach solid earth
ground wire (refer to
Figure 2.4 on page 23)
20

Section 2: Installation

STATIC SENSITIVE COMPONENTS
mounting slots
mounting studs
mounting slots
Figure 2.1 Chassis Mounting in Backbox
MRP-2002 Series Instruction Manual — P/N 53049:E5 7/28/2016
Main Circuit Board on Chassis
mounting holes
mounting tabs
Backbox

Advertisement

Table of Contents
loading

This manual is also suitable for:

Mrp-2002eMrp-2002c

Table of Contents