2 Unit Installation

2.6 Place provision

2.6.1 Place provision for RAS-(3-12)H(V)RNM(1)(E) and RAS-(4-10)H(V)RNS(1)E

¿
Concrete foundation
Foundation could be on flat and it is recommended to be 100-300 mm higher than ground level.
Install a drainage around foundation for smooth drain.
When installing the outdoor unit, fix it by M10 anchor bolts.
When installing the unit on a roof or a veranda, drain water sometimes turns into ice on a cold morning. Therefore, avoid
draining in an area that people often use because it may become slippery.
Metal plate for RAS-(3-6)H(V)RNM(1)E and RAS-(4-10)H(V)RNS(1)E
1
Outdoor unit.
2
Cut this portion of bolt If not, it's difficult to remove Service
cover.
3
Mortar hole (Ø100 x Depth 150).
4
Anchor bolt M10 (Ø12.5 Hole).
5
Drainage (Wide 100 x Depth 150).
6
Drainage.
7
Vibration-proof rubber.
N O T E
(*): Space for downward piping space.
Anchor bolt location in case of RAS-(8–12)HRNM
The whole base of the outdoor unit should be installed on a foundation. When using vibration-proof material, it should also
be positioned in the same place. When installing the outdoor unit on a fieldsupplied frame, use metal plates to adjust the
frame width for stable installation as shown in the figure below.
1. Outdoor unit is unstable
2. Frame.
3. Outdoor unit is stable.
4. Metal plate.
A. For RAS-(3-6)H(V)RNM(1)E 57 mm. Base width for outdoor unit.
For RAS-(4-10)H(V)RNS(1)E 70 mm. Base width for outdoor
unit.
For RAS-(8-12)HRNM: 100 mm. Base width for outdoor unit.
B. 60 mm. Frame width (Field supplied).
C. For RAS-(3-12)H(V)RNM(1)(E) 100 mm or more Metal plate.
For RAS-(4-10)H(V)RNS(1)E: 70 mm or more Metal plate.
22
SMGB0060 rev. 1- 12/2010
(1)
.
(1)
1
2
7
6
INCORRECT
A
3
2
B
1
2
3
4
5
4
CORRECT
A
4
C