Start-up protocol

14 Start-up protocol
Please check off all startup steps and record
measurements in the appropriate tables.
Start-up procedure
1.
Type of gas
2.
Has the leak test been completed?
3.
Check combustion air, inlet and outlet openings and flue gas connection
4.
Check the equipment (correct orifices? See below)
and convert gas type if necessary
5.
Fill boiler with water and bleed complete heating system
6.
Measure gas supply pressure (flow pressure)
7.
Measure manifold pressure and adjust if necessary
8.
Check pilot and main burner flame
9.
Leak check in operating status
10
Correct functioning of the venting system
11
Check maximum aquastat setting
12
Install front boiler door
13.
Inform operator, hand over technical documentation
14.
Installer:
Operator:
USER NOTE
Inform the customer of the correct fuel and
enter it in the table (operating manual of
boiler).
40
Installation and maintenance instructions Gas Boiler Logano GC124 II/SP • Issue 07/2006
Remarks or measured values
Natural gas
–––––––––––––––––––
–––––––––––––––––––
Signature:__________________
Signature:__________________
We reserve the right to make any changes due to technical modifications.
LP
inches W. C.
inches W. C.

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents