6
Placing the heating system in operation
Fig. 29 Install front panel of boiler
[1]
Locking screws
[2]
Boiler jacket
[3]
Front panel of boiler
6.8

Start-up protocol

Please check off the commissioning work as it is completed and record
the measured values in the table.
Commissioning operations
1.
Type of gas supply
2.
Check combustion air, inlet and outlet openings and flue
Check the appliance orifices (correct nozzles  Tab. 12), if necessary adjust gas
3.
type.
4.
Fill boiler with water and bleed complete heating system
5.
Measure gas supply pressure [inches W.C.] or [mbar]
6.
Measure nozzle pressure and adjust if necessary [inches W.C.] or [mbar]
7.
Leak test in operating status
Check of the ignition flame
Check of the main burner flame
Check of the perfect function of the venting system
8.
Check maximum AquaSmart
9.
Install front panel of boiler
10.
Inform operator, hand over technical documentation
11.
Installer:
Operator:
22
TM
setting
6.7
Inform owner/operator, hand over technical
documentation
Familiarize the owner/operator with the entire heating system and the
operating instructions for the boiler. Hand over the technical
documentation to the owner/operator and then both sign the
commissioning log on this page.
NOTICE: Risk of system damage due to freezing!
The heating system may freeze in frosty weather if it is
not switched on with the main switch or control unit.
▶ Protect the heating system against frost when
temperatures below freezing are expected.
▶ If the main switch or control is switched off, drain the
water from the boiler, the tank and the pipe of the
heating system.
Page
Comments or measured value
Natural Gas
page 14
page 23
page 13
page 20
Measurement
value:__________ Unit_____
page 20
Measurement
value:__________ Unit_____
page 18
page 20
page 20
page 21
page 21
page 22
Signature:_________________
Signature:_________________