Platform Installations and Upgrades
4. Connect all cables to the server board.
Note:
If you forgot to install your SCSI cable prior to installing the server board, or
you need to replace the SCSI cable without replacing the server board, secure
the SCSI cable to the board connector and make sure it is fully seated with a
#2 flat-blade screwdriver, as shown in the figure below.

Figure 55. Securing SCSI Cable to Server Board Connector

5. Install the four-fan assembly. For instructions, see
6. Install the processor and heat sink. For instructions, see
7. Install all DIMMs. For instructions, see
8. Push the handle on the front panel to baseboard connector towards the rear of the
chassis.
9. Install the processor air duct. For instructions, see
10. Install the PCI riser assembly. For instructions, see
11. Install the chassis cover. For instructions, see
76
"Installing the Four-Fan Assembly."
"Installing the Processor."
"Installing DIMMs."
"Installing the Processor Air Duct."
"Installing a PCI Add-in Card."