Omron KP100L-OD - 12-2010 User Manual page 89

Gridconnect photovoltaic inverter
Table of Contents

Advertisement

3 Operation
Error of Auto Test
The measurement becomes impossible when the power failure etc. occur, the LCD display shows "Example 1" ,
so the Auto Test error "E5-9 AutoTestFault" occurs, and KP100L stops. Afterwards, you can execute Auto Test
again according to the procedure of "The starting procedures for auto test".
[Examle 1]
AutoTest:UF
- - -
/
- - -
Change of Set Value
The detect level of OF/UF can be changed according to the detect level change menu of the user setting as
follows. The setting should be 0 (OF is 50.50Hz and UF is 49.70Hz) as default.
You don't allow to change setting to 1 without ENEL agreement. You can only change setting by indication of
ENEL personnel as described in ENEL gideline.
Setting
OF/UF Detect level
50.30Hz (OF-Detect level)
0
49.70Hz (UF-Detect level)
51.00Hz (OF-Detect level)
1
49.00Hz (UF-Detect level)
 Setting of Germany
This section explains the setting when the country setting is Germany.
Change of Detect level
The detect level of OV can be changed according to the detect level change menu of the user setting as follows.
You can only change setting in consultation with grid operator
Setting
OV Detect level
0
253.00V
1
264.50V
3 - 26
Grid Connect Photovoltaic Inverter KP100L-OD- USER'S MANUAL

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Kp100l-od series