Omron KP100L-OD - 12-2010 User Manual page 87

Gridconnect photovoltaic inverter
Table of Contents

Advertisement

3 Operation
Items
Sequences during the auto test
(5)
(5-1)The inverter turns on the inside Grid-connected
The Auto
relay
Test of
(5-2)Detect level of UV [L2] is increased at the point of
UV [L2]
0.5V/s
(5-3)Grid-connected relays are disconnected, when UV
[L2] detect level keeps above the grid voltage for
more than UV [L2] detect time
(5-4)Detect level and detect time of UV [L2] detected in
(5-3) are shown. (Display for ten seconds.)
(6)
(6-1)The inverter turns on the inside Grid-connected
The Auto
relay
Test of
(6-2)Detect level of UV [L3] is increased at the point of
UV [L3]
0.5V/s
(6-3)Grid-connected relays are disconnected, when UV
[L3] detect level keeps above the grid voltage for
more than UV [L3] detect time
(6-4)Detect level and detect time of UV [L3] detected in
(6-3) are shown. (Display for ten seconds.)
3 - 24
AutoTest:UV [L2]
230.02V / 184.00V
The grid voltage of L2
[e.g.] in the case of 230.02V
Setup level of UV [L2]
[e.g.] in the case of 184.00V
Result of UV phase L2
AutoTest:UV [L2]
230.04V /
Detect level of UV [L2]
[e.g.] in the case of 230.04V
Detect time of UV [L2]
[e.g.] in the case of 110ms
After displaying for ten seconds,
start the auto test of UV [L3]
AutoTest:UV [L3]
230.02V / 184.00V
The grid voltage of L3
[e.g.] in the case of 230.02V
Setup level of UV [L3]
[e.g.] in the case of 184.00V
Result of UV phase L3
AutoTest:UV [L3]
230.04V /
Detect level of UV [L3]
[e.g.] in the case of 230.04V
Detect time of UV [L3]
[e.g.] in the case of 110ms
After displaying for ten seconds,
start the auto test of OF
Grid Connect Photovoltaic Inverter KP100L-OD- USER'S MANUAL
LCD
110ms