Clearance Requirements for Airflow and Hardware Maintenance for
ACX5400 Routers
When planning the site for installing an ACX5400 router, you must allow sufficient clearance around the
installed chassis (see
Figure 40 on page 70
Figure 40: Clearance Requirements for Airflow and Hardware Maintenance for ACX5448 and ACX5448-D
Routers
24 in.
(61 cm)
Clearance required
for maintenance
Ports
17.26 in.
(43.84 cm)
Figure 41: Clearance Requirements for Airflow and Hardware Maintenance for ACX5448-M Routers
24 in.
(61 cm)
Clearance required
for maintenance
Ports
17.26 in.
(43.84 cm)
and
Figure 41 on page
21.81 in.
( 55.41 cm)
(48.2 cm)
20 .29 in.
( 51.53 cm)
25.50 in.
(64.75 cm)
19 in.
(48.2 cm)
24.0 in.
(61.0 cm)
70).
24.0 in.
(61 cm)
Clearance required
for maintenance
FRUs
19 in.
24.0 in.
(61 cm)
Clearance required
for maintenance
FRUs
70