Restoring Drive Canister Power - IBM 3592 Maintenance Information

Rack mount models
Hide thumbs Also See for 3592:
Table of Contents

Advertisement

Figure 64: Rack service position - rear view
To power OFF the drive, complete the following steps:
1. If the device is not varied offline, have the customer vary (take) it offline at the host.
2. Ensure that the customer's job is complete.
3. Unless this call is for a Tape Unload problem, press Unload on the Operator bezel (see Figure 2 on
page 29) to eject any currently loaded tape cartridge. It can take up to 5 minutes for the cartridge to
rewind and unload. When the unload is complete, remove the cartridge from the drive.
4. Unhook the retaining strap (
5. Unplug the power connector (
6. If the procedure that sent you here calls for removing the drive canister from the rack, go to "Removing
the drive canister from an enclosure" on page 253.

Restoring drive canister power

If the drive canister is not already installed in the rack, go to "Replacing or reinstalling the drive canister"
on page 254, and then return here.
1. Plug in the power connector (
2. Reattach the retaining strap (
Note: Wait at least 5 seconds after power is removed from the 3592 tape drive before power is restored.
The power-on self-test (POST) runs when power is applied to the drive canister. This POST takes less than
1 minute to complete. When power is restored, the Operator 8-character display (see Figure 2 on page
29) initially displays BOOTING. Then, while the POST test is running, the display shows DIAGS*. If POST
completes successfully, the display changes from DIAGS* to blank.
184 IBM 3592 TS1140, TS1150, TS1155, and TS1160 Tape Drives: Maintenance Information
2
1
).
2
). The power cables are not shown.
2
in Figure 64 on page 184).
1
in Figure 64 on page 184).
1