8.4

Commissioning with steam or liquid

Overview
Figure 8-1
(1)
(2)
(2A)
(2B)
(3)
(4)
(5)
(6)
Requirement
All valves are closed.
Procedure
To commission the transmitter for steam or liquid, proceed as follows:
1. Open the shut-off valve for the test connection (2B).
2. Via the test connection of the shut-off module (2), apply the pressure corresponding to
3. Check the zero point.
4. If the zero point differs from the value desired, correct it.
5. Close the shut-off valve for the test connection (2B).
SITRANS P300 with HART communication
Operating Instructions, 06/2005, A5E00359579-02
Measuring steam
Pressure transmitter
Shut-off module
Shut-off valve to process
Shut-off valve for test connection or for bleed screw
Pressure line
Shut-off valve
Drain valve
Compensation vessel (steam only)
the zero point to the pressure transmitter (1).
8.4 Commissioning with steam or liquid