8.
Disconnect all the FFCs connected on the CR Relay Board.
CN1: Printhead
CN2: Printhead
CN3: Main Board
CN4: Main Board
CN3
CN1
CN2
Figure 4-42. Removing the CSIC Assy (2)
9.
Remove the C.B.S. M3 x 6 screw that secure the CR Relay Board, and remove the
CR Relay Board from the Carriage Unit.
CR Relay Board
2) C.B.S. M3x6
(6±1 kgf.cm)
Figure 4-43. Removing the CSIC Assy (3)
Disassembly And Assembly
10. Release the two hooks; located on both the left side and the right side of the CSIC
CN4
Disassembling the Printer Mechanism
Assy, and remove the CSIC Assy upward.
Hook
CSIC Assy
Hook
Figure 4-44. Removing the CSIC Assy (4)
Revision C
Hook
CSIC Assy
Hook
Confidential