Cabling the Indoor Control Panel at the Load Center

To connect the Indoor Control Panel cable to the Personality board:
1. Turn off the main system power before making any connections.
2. Run a UL approved four conductor cable (22 AWG) from the Indoor Control Panel to the
Load Center. The preferred wire color scheme is: Red, yellow, green, and black.
CAUTION Do NOT short GND or +15V connections (Red or Black) to data lines (Green or
Yellow). The Control Panel board may be permanently damaged. Do NOT reverse GND or +15V or
system will not operate.
3. Route the cable up through the low voltage raceway to the Personality board. To access the
Personality board, refer to Installing the Outdoor Control Panel, page 16.
4. Strip back the communication cable conductors ¼ in. Insert the wires into the screw
terminals (provided in the kit). Secure the wires with the screws. Make sure to match the
color-coding of the wires: Red = +15, Yellow = +DT, Green = -DT, and GND = Black.
5. Insert the cable plug onto either of the COM PORTS (J7 or J8) connectors located on the
left side of the Personality board. For connector locations, refer to the Wiring Diagrams on
pages 32 and 33.
6. Proceed with Cabling the Indoor Control Panel, page 24.
BLK
GRN
YEL
RED
Personality board
(Connector J7 or J8)
IntelliTouch Personality Kit Installation Guide
23