Installation and Wiring with a Powerware 9390 UPS

EATON Powerware

Powerware Sync Control Installation

S
Only qualified service personnel (such as a licensed electrician) shall perform the electrical installation. Risk
of electrical shock.
S
Shut down all sources of power to the Powerware 9390 or Powerware 9395 UPS system before connecting
the control wiring to the Powerware Sync Control enclosure and UPS. Hazardous voltages exist inside the
UPS and in the Powerware Sync Control enclosure. Check all terminal conductors with a known serviceable
voltmeter before connecting the wiring.
Once the Powerware Sync Control has been moved to its installed location,
unpacked, and inspected, it is ready for installation and wiring.
Use the applicable procedure from the following list to install the Powerware Sync
Control to the UPS:
S
With a Powerware 9390 UPS, proceed to paragraph 3.1.
S
With a Powerware 9395 UPS, proceed to paragraph 3.2.
NOTE When installing wiring connections, conduit must be installed between the Powerware Sync Control and
the UPS cabinet. Conduit also must be installed between the Powerware Sync Control and the customer's remote
monitoring system.
To install and wire:
1.
Install the Powerware Sync Control panel to the selected mounting location.
See Figure 2-1 on page 2−2 for mounting hole dimensions and Figure 2-2 on
page 2−3 for conduit entrance locations.
2.
Unfasten the front door latches and swing the door open.
3.
Complete all control wiring interconnections using Table 3-1 for wiring
requirements.
Figure 3-1 on page 3−3 shows the Powerware Sync Control TB1 terminal block
and ground terminal locations. Figure 3-2 on page 3−4 shows the TB1 terminal
block wiring detail.
Figure 3-3 on page 3−5 and Figure 3-4 on page 3−6 show the typical locations of
the UPS TB1, TB2, and TB6 interconnect terminal blocks. Figure 3-5 on
page 3−6 shows the TB6 detail.
Refer to the applicable Powerware 9390 UPS Installation and Operation Manual
listed in paragraph 1.3 on page 1−4 for UPS cabinet terminal locations and
assignments, termination requirements, conduit landing locations, and terminal
access instructions.
4.
Verify the jumper is installed between Sync Control terminal TB1−40 and TB1−41
(see Figure 3-2 on page 3−4).
®
9390 and 9395 Sync Control Installation and Operation Manual
W A R N I N G
S
164201571 Rev E www.powerware.com
3−1

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Powerware 9395

Table of Contents