Operation Test
Confirm the entered system data and hardware, including cable connection, by completing the following oper-
ational tests.
Basic Connection Test at MDF
Station Line Test (Operator Call from all stations)
Central Office Trunk Test (Incoming, Outgoing)
Tie Line Trunk Test (Incoming, Outgoing)
Service Feature Test
Call Transfer
Step Call
Executive Right of Way
Call Hold
Call Back
Call Forwarding-All Calls/Don't Answer/Busy Line
Call Pickup
Station Hunting-Pilot/Circular
Speed Calling-System/Station
Paging Access
Announcement Service
etc.