To complete the installation, perform the following procedure:
1. Install an uninterruptible power supply according to the manufacturer's
instructions.
2. Plug the power cable from the gateway into the UPS.
3. Turn on the UPS.
4. If necessary, plug the management cable into the console port, as
shown in Figure 56.

Figure 56. Connecting the Management Cable

Note
For networks with remote management enabled, no local
configuration is required.
5. Configure the AT-iMG646xx series intelligent multiservice gateway
according to your specifications and then unplug the management
cable.
6. Ensure that all provisioned services are functioning properly.
1193
Section II: Indoor Installation

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

At-img646px-onAt-img646bd-on

Table of Contents

Save Article as PDF