McDATA 316095-B21 - StorageWorks Edge Switch 2/24 Installation And Service Manual page 244

Fabric switches
Hide thumbs Also See for 316095-B21 - StorageWorks Edge Switch 2/24:
Table of Contents

Advertisement

Diagnostics
3
McDATA® Sphereon 3032 and 3232 Fabric Switches Installation and Service Manual
3-30
b. Ensure the AC power cord is not damaged. If damaged, replace
the cord.
Was a corrective action performed?
YES
NO
Go to
step
8.
7
Verify power supply operation.
a. Inspect the power supply and ensure the green LED illuminates.
b. At the Hardware View, observe the graphic representing the
power supply and ensure a failure symbol (blinking red and
yellow diamond) does not appear.
Is a failure indicated?
YES
NO
The switch appears operational.
8
Ensure the power supply is correctly installed and seated in the CTP
card. If required, partially remove and reseat the power supply.
Was a corrective action performed?
YES
NO
Go to
step
10.
9
Verify power supply operation.
a. Inspect the power supply and ensure the green LED illuminates.
b. At the Hardware View, observe the graphic representing the
power supply and ensure a failure symbol (blinking red and
yellow diamond) does not appear.
Is a failure indicated?
YES
NO
The switch appears operational.
10
A redundant power supply failed and must be removed and replaced.
(RRP: Power Supply
on page 5-4).