8. Electrical Installation
8.1.
Electrical Installation quick reference diagram
Check Supply Voltage does not exceed drive Voltage rating as shown on rating label.
Check the number of supply phases is compatible with the drive as shown on rating label.
If the power supply has a low supply impedance /high short circuit current a Line
reactor/Isolation transformer maybe required.
For generator Bourne power supplies please contact your Invertek sales partner for further
guidance.
Ensure there is at least 30 seconds between each power-on.
Install suitably rated fuses/Circuit breakers
If an earth leakage detection device is used (e.g.ELCB/RCD), a type B trip characteristic
which is suitable for protecting equipment with a DC component should be used, 1 device
for multiple drives should be avoided.
Install Line reactor as close to the drive as possible and under the following conditions:
If phase-phase imbalance is >3% (3Ø drives).
To reduce Inrush current.
If power supply has a low supply impedance/high short circuit current.
If power supply is prone to dips or brown-outs.
If power supply is via a bus-bar and sliding contacts system.
Reduction in mains Harmonic emission.
Install External EMC filter if the motor cable length exceeds the Electromagnetic
interference reduction capability of the internal filter
Do Not Use EMC filters on IT (Ungrounded) or a corner grounded TN power supply systems.
Functionality of control terminals is pre-configured according to parameter P1-02, default
functionality is shown below :
DI1
DI2
DI3
Open
Open
Open
Disabled/
Disabled/
Disabled/
Levelling
Close
Close
Speed
Forward
Reverse
(P8-05)
The drive will only start if all the below conditions are met:
Safe Torque off inputs are enabled.
A direction Command (DI1 or DI2) has been given.
At least 1 speed has been selected.
Note : If more than 1 speed selection input is high the highest speed will be used.
Install Output Choke under the following conditions:
If cable between the drive and motor exceeds 100m (screened cable), or 150m (un-screened
cable).
If motor is not "inverter rated".
Encoder Wiring:
The encoder cable should be screened, ideally with each signal pair individually screened. The
screen should be connected to the 0V of the encoder module, or shield/screen connection.
www.InvertekDrives.com
DI4
DI5
DI6
Open
Open
Open
Disabled/
Disabled/
Disabled/
High
High
Inspection
Speed
Speed 5
Speed
(P8-06)
(P8-12)
(P8-08)
DI7
DI8
Rescue
Fault
Mode
Reset
Enable

Advertisement

loading
Need help?

Need help?

Do you have a question about the elevator CORE and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel