INSTALLATION MAIN STEPS:
1.
Drill holes with the hammer according to the model dimensions specified above.
2.
Once hole is done with hammer driller, it is strictly necessary to:
- Blow twice the bottom of the hole with compressed air (min 6 bar pressure).
- Brush twice the hole with a wire brush.
- Blow twice again the bottom of the hole with compressed air (min 6 bar
pressure).
3.
Introduce the injection resin in each hole as specified in manufaturer's datasheet.
4.
Introduce the anchor rod in each hole as specified in manufaturer's datasheet.
5.
Place the Charge Point using the anchor rod introduced and tighten the washer.
Notes:
1.
The calculations described above are as a reference use only. If necessary, ask
Circontrol Support Department
original report regarding fixing the Charge Point.
2.
In the event of any doubt about the terrain regarding the installation of the Charge
Point or use of another model of injection mortar, it will be necessary to define a
final solution to install the unit. It must be confirmed by a specific technical project
made for an architectural firm prior to its installation.
39
support@circontrol.com
CIRCONTROL — Raption HPC Installation Manual
in order to download the

Advertisement

loading
Need help?

Need help?

Do you have a question about the Raption HPC and is the answer not in the manual?