POST INSTALLATION TEST
FCCS Network Connection Test
3.4 3-party Conference Trunk Function Test (via FCCS)
Perform the 3-party conference trunk function test, following the procedures listed below.
STEP 1: Using the MBTK Command, make busy all 3-party Conference Trunk (CFTs) except the trunk to be
tested.
STEP 2: Establish a station-to-station connection between STNs A and B in self node (Node A).
STEP 3: STN A goes to Switch Hook Flash (SHF), and after hearing SPDT, dials the Telephone Number of
STN C in other node (Node B).
STEP 4: STN C answers the call.
STEP 5: STN A, after a brief talk with STN C, makes a SHF, and confirms that a three-way connection has
been set up.
STEP 6: Release the call.
STEP 7: Repeat the above steps for all CFTs.
STEP 8: Using the MBTK command, cancel the make-busy status of the trunk.
Node A (Self-Node)
SHF
+
TELN: 420000
LC
STN A
TELN: 410000
STN: 2000
LC
STN B
TELN: 410001
STN: 2001

Figure 6-11 3-party Conference Trunk Function Test via FCCS

When a station activates this feature, CFT in Self-Node is used. In this case, CFT in Node A is used.
Note:
3.5 FCCS Alternate Routing Test
This section explains how to perform the test for Fusion-link alternate routing. Following the procedures
below, make sure that the connection and alternate routing to all FCCS lines are normal and correctly es-
tablished.
CHAPTER 6
Page 142
Revision 3.0
RBT,
SPDT
FCCS
C
F
T
TSW / MUX Card
ND-70185 (E)
Get other manuals https://www.bkmanuals.com
Node B
LC
STN C
TELN: 420000
STN: 2000
RG
Check

Advertisement

Table of Contents
loading

Table of Contents