TROUBLESHOOTING
23-S FCH Failure Notification (Detection)
7.1 Repair Procedure
STEP 1: Make sure that the related Ethernet cables are securely inserted into the connectors. (See the example
shown below.) If not, securely insert the cable. In this instance, confirm whether System Message 23-
T FCH Fault Recovery Notification is displayed as the result of cable insertion. If no fault is found
in this step, move to STEP 2.
STEP 2: The following equipment is suspected to be faulty. Check for each item:
Ethernet cables (10 BASE-T cables) ← See
HUB (PA-M96) ← See
FCH (PA-FCHA) ← See
PIM 1
PIM 0
: 10 BASE-T cable
Note: 10 BASE-T cable connections may differ depending on system configuration.
CHAPTER 7
Page 156
Revision 3.0
Figure 7-14
"How to Replace HUB (PA-M96) card."
Figure 7-4
"How to Replace FCH (PA-FCHA) card."
FCH (PA-FCHA)
FCH card indicated
by system message
HUB
(PA-M96)

Figure 7-12 10 BASE-T Cable Connection Check

ND-70185 (E)
Get other manuals https://www.bkmanuals.com
Figure 7-13
"How to Check 10 BASE-T cables."
DTI
DTI
HUB
(PA-M96)
LANI
LANI
ATTENTION