3.5.1
Primary Route Trunk Test
STEP 1: Using the MBCT command, make busy all trunks in the primary route except the trunk to be tested.
STEP 2: Lift the handset of STN A in self-node (Node A).
STEP 3: Dial the Telephone Number of STN B which belongs to other node (STN B).
STEP 4: Confirm the speech condition is sufficient (no noise, not one-way speech, etc.).
STEP 5: Replace the handset of STN A.
STEP 6: Make idle all the trunks which were placed in make-busy state in STEP 1.
3.5.2
Alternate Route Trunk Test
STEP 1: Using the MBCT command, make busy all trunks in the primary route.
STEP 2: Using the MBCT command, make busy all trunks in the alternate route except the trunk to be tested.
STEP 3: Lift the handset of STN A.
STEP 4: Dial the Telephone Number of STN B.
STEP 5: Confirm the speech condition is sufficient (no noise, not one-way speech, etc.).
STEP 6: Replace the handset of STN A.
STEP 7: Make idle all the trunks which were placed in make-busy state in STEP 1 and STEP 2.
Node A
(Self-Node)
STN A
TELN: 410000
STN: 2000
4. Fusion and Non-Fusion Connection Tests
Use the following procedures to perform the connection test between the FCCS and non-Fusion Common Chan-
nel Interoffice Signaling (CCIS) or Associated Channel Interoffice Signaling (ACIS):
Primary Route
Alternate Route

Figure 6-12 Fusion Alternate Routing Test

ND-70185 (E)
Get other manuals https://www.bkmanuals.com
Fusion and Non-Fusion Connection Tests
Node C
Node D
POST INSTALLATION TEST
Check
Check
Node B
STN B
TELN: 420000
STN: 2000
CHAPTER 6