SERIES 1500 LIQUID TURBINE METER
Planned maintenance
September 2020
9.4.2
Assemble internal meter housing components - NPS 1.5,
2 and 2.5
Prerequisites
Important
Clean all surfaces of the equipment to prevent meter damage.
Procedure
90
80
www.Daniel.com
1. For NPS 2 and 2.5 meters place the upstream spring clip assembly, small washer
end first, into the upstream end of the housing. Push the spring clip assembly into
the bore to shoulder. For NPS 1.5 meter place the thrust washer in counterbore of
the upstream cone face, polished side out. Place the upstream spring clip assembly
cone end first into the upstream end of the housing. Push the assembly into the
bore to shoulder.
Figure 9-21: Spring clip assembly and thrust washer installation
2. Insert the end of the shaft into the center hole of the upstream end of the upstream
spring clip assembly. For NPS 1.5 meter, be careful not to knock the thrust washer
out of the cone counterbore.