Chapter 3 Installing the Library

Leveling the Library

Leveling the Library
24
Quantum|ATL 7100 Series Facilities Planning and Installation Guide
• Digital voltmeter (DVM)
• ESD protection kit
To level the library:
Completing this task involves leveling one side of the
Note:
library at a time, moving in a clockwise direction starting
at the front and ending with the right-side of the library.
Move the library onto its designated footprint in the final
1
installation area.
Lower each foot of the library until it makes contact with the
2
floor.
When adjusting the feet for leveling purposes,
Caution:
DO NOT raise any foot so high that excess weight
is transferred to any single caster.
Moving in a clockwise direction from the library front, rotate
3
each foot clockwise so that each caster is raised approximately
1/4" off of the floor.
Center a carpenter's level on the top front edge of the library.
4
Check the gauge on the level. If the front of the library is level,
5
proceed to step 6. If it is not level:
Determine the tilt of the library and adjust the appropriate
a
front foot with the wrench, checking the gauge each time
that a foot is rotated ¼ turn.
Repeat step 5 until the front is level, then continue to the
b
next step.
Center the carpenter's level on the top left edge of the library.
6
3