The UPS system installation must meet the following guidelines:
• The system must be installed on a level floor suitable for computer or electronic equipment.
• The system must be installed in a temperature and humidity controlled indoor area free of conductive
contaminants.
Failure to follow guidelines may void your warranty.
The UPS equipment operating environment must meet the weight requirements shown in Table 3-1 and the
size requirements shown in Figure 3-1. Dimensions are in millimetres (inches).
HIGH TOUCH CURRENT EARTH CONNECTION ESSENTIAL BEFORE CONNECTING SUPPLY.
As a result of the connected loads high leakage current is possible. Connection of the earth
(ground) is required for proper product operation. Do not check UPS operation by removal of
the Earth (ground) connection.
The UPS unit is not suitable for IT and corner-earthed power distribution systems.
RISK OF ELECTRIC SHOCK. This ups receives power from more than one source -
disconnection of the AC and the DC source is required to de - energise this unit before
servicing. After disconnecting the utility power and the DC power, authorised service
personnel should wait at least five minutes for capacitor bleedoff before attempting internal
access to the UPS module.
Backfeed protection is an internally fitted option on this device. If this option, or an externally
fitted backfeed contactor are not installed.
The below label should be applied on all primary power isolators installed remote from the
UPS area and on external access points.
• Refer to national and local electrical codes for acceptable external wiring practices.
• To allow for future kVA upgrades, consider installing a derated UPS using wiring and external overcurrent
protection breakers sized for a fully rated UPS.
• For external wiring, use 90°C copper wire. Wire sizes listed in Table 3-5 are for copper wiring only. If wire is
run in an ambient temperature greater than 30°C, higher temperature wire and/or larger size wire may be
necessary. Wire sizes are based on using the specified breakers.
• Material and labour for external wiring requirements are to be supplied by designated personnel.
• If installing an external maintenance bypass, all feeds to the UPS including the Rectifier Input Breaker (RIB)
(if installed) must have a service disconnect independent of the maintenance bypass power path. Most
maintenance bypass solutions provide UPS input feeds derived from but isolated from the maintenance
bypass power path. If the maintenance bypass solution being installed does not provide such functionality,
DO NOT use a single feeder breaker to supply both the UPS and the maintenance bypass.
WARNING
WARNING
Eaton 93E UPS (15-80 kVA, 380/400/415V) Installation and Operation Manual
UPS Installation Plan and Unpacking
CAPACITORS INSIDE
REQUIRE 5 MINUTES
TO DISCHARGE
TO A SAFE LEVEL
AFTER ALL POWER
IS REMOVED.
SEE HANDBOOK
FOR INSTRUCTIONS.
3-15

Advertisement

Table of Contents
loading

Table of Contents