ELECTRO FREEZE Soft Serve Model GEN-5400
8
Assembly
ROLLER SUPPORT HOUSING
B) SWING BACK
SHOE CLAMP
Figure 8-7 MTS
MTS hose assembly by first placing the
clamp next to the braided hose, above
the roller bearing support on the right side
and push hose into slot. Place the transfer
hose under the rollers. While holding the
pickup tube stretch the hose so the left
hand clamp is above the roller bearing
support and push the hose into the slot.
Do not twist the hose assembly while
installing.
hose is straight and centered on the
roller assembly making sure the locating
line is facing out. The line should be in
the same position at the inlet and outlet
guides of the roller bearing support, as
shown in figure 8-7.
30
(continued)
CYLINDER INLET
D) LOOSEN CLAMP
E) PULL TUBE OFF
CYLINDER INLET
AND REMOVE
18. Refer to figure 8-7. Install the
Important:
19. Check to ensure the transfer
20. Swing the shoe over hose and
C) SWING OPEN
ROLLER SHOE
A) LOOSEN KNOB
tighten the swing clamp hand knob in
place until it bottoms out and will not turn
any further.
21. Insert the air tube into the
retainer in the back of the cabinet.
22. Insert the MTS cover over stud
see figure 8-8. Hose clamps should be
exposed. Tighten cover knob. Hand
tighten only.
The MTS will not operate unless the
cover is installed and secured by the
hand knob.
23. Loop the braided hose towards
you and slide the hose over the cylinder
inlet tube. Tighten the clamp. Make sure
the braided hose is not twisting transfer
hose.
Important:
—continued
184297