Commissioning The Appliance; Chimney Sweep Menu - REMEHA Gas 210 Ace 80 Service Manual

High-efficiency standing gas boiler
Hide thumbs Also See for Gas 210 Ace 80:
Table of Contents

Advertisement

4 Installer instructions
4.4

Commissioning the appliance

4.4.1

Chimney sweep menu

Fig.14
Load test
11:20
... ......
.... ...... ....
.....
i
..... ... ....... .... .. ..... ....... .... ..... .......
....... .... ....... .... .......
..... ... ....... .... .. ..... ....
.....
....... .... .. ..... ....
....... ...........
..... ... ....... ....
..... ... ....... ....
Tab.9
Load tests in the chimney sweep menu
Change load test mode
Off
Low power
Medium power
High power
Tab.10
Load test settings
Load Test menu
Func test status
System Flow Temp
T return
Actual fan RPM
Actual flame current
Fan RPM Max CH
Fan RPM Min
Fan RPM Start
12
At first start-up of the appliance, the display will show the commissioning
wizard. Depending on the appliance, some steps take a few minutes to
complete, for example appliances that need to deaerate after installation
or need to configure a boiler.
Select the tile [
test mode menu will appear:
A
.........
.......
...
......
.....
B
AD-3000941-03
Settings
No test
Part load test
Full load test for Central Heating mode
Full load test for Central Heating + Domestic Hot Water mode
Settings
Select the load test to start the test.
Read the central heating flow temperature
Read the central heating return temperature
Read the actual fan speed
Read the actual flame current
Adjust the maximum fan speed during Central Heating mode
Adjust the minimum fan speed during Central Heating + Domestic Hot Water mode
Adjust the start fan speed
Use the rotary knob to navigate.
Use the
button to confirm your selection.
1. Start up the appliance.
2. Follow the instructions on the display.
Important
The appliance might take a few minutes during certain steps while
commissioning. Do not shut off the appliance or try to bypass
steps, unless stated otherwise on the display.
3. You can access individual commissioning steps:
3.1. Press the
button.
3.2. Select Commissioning Menu.
3.3. Select the commissioning step you wish to perform.
] to open the chimney sweep menu. The Change load
A Change load test mode
B Load test mode
See also
Checking/setting values for O2/CO2 at full load, page 47
Checking/setting values for O2/CO2 at low load, page 48