Commissioning
4.2 First startup
At first startup, user has to feed in AC power and switch on the manual switch
and DC Power Switch. Inverter will start up and LCD display panel will turn on
when powered on through AC. Please set language and the correct country
(Grid Code) according to your region and wait for the AFCI Self Test.
Please make sure that there is no any error, fault or warning showing on home
page. Now you can feed in DC power and wait for inverter initially self-test
about 2 minutes. If there is enough power generated from PV array, inverter
will start feeding in power to grid.
The following Figure 4-2 illustrates the display flow charts of the inverter startup.
First Startup
Select Language,
►
English
Deutsch
Français
When setting is
IEEE1547
Pass: to Home page
Fail : to Home page but in locked status and indicated "AFCI fail"
Figure 4-2 : Country ,language and ID settings for first startup
Select Grid Code,
ENT
►
IEEE1547
BDEW
NB/T32004
EXIT
AFCI
Self Testing . . .
38
Are you sure to set
ENT
Grid Code :
XXXXXXXXXXXXX
EXIT
AFCI Self Test
Result: Pass
Pass / Fail
ENT
Yes / ►No
ENT
EXIT