5. Unit installation
WARNING
• Be sure to remove the wood en pallet from the bottom side of the unit base panel before fixing the unit
with bolts to the floor.
Its sole purpose it to carry the product during transport, it has no installation value. Please discard the
pallet in accordance to local waste regulations once the unit is correctly installed.

To install the indoor unit

1 Considering the vibration and weight of the Tank integrated hydro unit, the structural strength of the base ground
must be strong enough to prevent noise and the base ground has to be flat.
2 The base ground should be 1.5 times larger than the bottom of the Tank integrated hydro unit.
3 Lift the indoor unit from the pallet and place it on the floor, be careful not to scratch the floor by sharp edges or bolts.
4 Connect the drain hose to the drain.
5 Slide the indoor unit into position.
6 Adjust the height of the leveling feet to compensate for floor irregularities.
7 When concrete construction for Tank integrated hydro unit installation is completed, install an anti-vibration pad
(t = 20 mm or more) or an anti-vibration frame (vibration transmission ≤ 5%) to prevent vibration of the indoor unit
from transferring to the base ground.
Installer reference guide / Mono tank integrated type
48