Step 4 Select System Func > Diagnosis > Self Test on home screen, and the unit will
start the "self-test" procedure automatically.
Step 5 If the self-test is passed, the system enters the normal running status. Internal
cycle fan keeps running. If the cabinet internal temperature reaches the cooling
startup point, the cooling will start, and then compressor and external fan run at
the same time.
----End
9.2.2 (Optional) Commissioning the Intelligent Heat
Exchanger
Prerequisites
The power-on commissioning for the upstream PDC of the intelligent heat
exchanger is completed, and the intelligent heat exchanger has been powered on.
Understand the power-on commissioning process.
Procedure
Step 1 Switch on the AC and DC input circuit breakers, enter the Main Menu and choose
System Func > Diagnosis > SelfTest.
Step 2 The smart cooling product operates properly after the self-test is successful.
Issue 03 (2022-12-15)
Figure 9-3 Teamwork setting
NO TE
For more details please see the documents delivered with the intelligent heat exchanger.