Daikin RXTA30B2V1B Service Manual page 52

R32 optimized heating 4 split
Hide thumbs Also See for RXTA30B2V1B:
Table of Contents

Advertisement

4
|
Components
To perform a position check of the 4-way valve
Service manual
52
1 First perform an electrical check of the 4‑way valve, see
4
procedures" [
 50].
When outdoor temperature is mild and unit can switch between heating and
cooling
INFORMATION
This procedure is ONLY possible when the outdoor temperature is within the
temperature range for both Heating and Cooling operation mode. See the
databook on Business Portal for the temperature range of the operation modes.
1 Activate Heating operation via the user interface.
INFORMATION
It is recommended to connect the service monitoring tool to the unit and verify the
operation mode of the 4-way valve.
2 Check with a contact thermometer (or by touching) if the flow through the 4-
way valve corresponds with the flow shown in the flow diagram. (See
"7.3 Piping
diagram" [
INFORMATION
The flow through the 4-way valve is correct if the water temperature after the heat
exchanger rises/drops when operating in Heating/Cooling mode.
Is the flow correct?
Yes
No
3 Connect a manifold to one of the service ports of the refrigerant circuit and
check the pressure (suction, discharge). Compare with normal operation
conditions of the unit.
Refrigerant pressure correct?
Yes
No
4 De-activate Heating and activate Cooling operation via the user interface.
5 Check with a contact thermometer (or by touching) if the flow through the 4-
way valve corresponds with the flow shown in the flow diagram. (See
"7.3 Piping
diagram" [
INFORMATION
The flow through the 4-way valve is correct if the water temperature after the heat
exchanger rises/drops when operating in Heating/Cooling mode.
4
 242]).
Action
Skip the next step of this procedure.
Perform the next step of this procedure.
Action
Replace the body of the 4‑way valve,
see
"4.1.2 Repair
Leaks may be found in the refrigerant
circuit. Perform a pressure test of the
refrigerant circuit, see
procedures" [
4
 242]).
RXTM-R+RXTP-R+ARXTP-R+RXTA-B+FTXTA30B2V1B(W)
(B)+FTXTM30+40R2V1B+FTXTP25+35M5V1B+ATXTP25+35M5V1B
"4.1.1  Checking
procedures" [
4
 53].
"5.2.1 Checking
4
 211].
R32 Optimized Heating 4 Split
ESIE21-12A – 2022.02