Sungrow SG5.0RS-ADA User Manual page 65

1-phase pv grid-connected inverter
Hide thumbs Also See for SG5.0RS-ADA:
Table of Contents

Advertisement

User Manual
step 8 Enter the Activate EasyConnect interface, and press the multi-function button on the
WiNet-S to enable the Easyconnect mode according to the prompt on the screen. The App
automatically enters a waiting processing interface if this mode is enabled, and automatically
returns to the commissioning interface after the processing is completed.
Only the 2.4 GHz working band is supported under the networking mode.
If the Easyconnect fails, please refer to other methods in the WiNet-S manual to es-
tablish the connection.
step 9 Tap Device Initialization to go to the Device initialization interface. Set the initialization
protection parameters as needed and tap Settings to return to the commissioning interface.
6 Commissioning
55

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sg8.0rsSg9.0rsSg10rs

Table of Contents