User Manual
step 5 Fix all the wires to the terminals according to the assignment and tighten to a torque of 2.0
N•m with a screwdriver.
Observe the terminal assignment. Do not connect any phase line to the "PE" termi-
nal or PE wire to "N" terminal. Otherwise, unrecoverable damage to the inverter
may follow.
step 6 Secure the AC waterproof cover to the inverter with a torque of 1.0 N•m and tighten the swiv-
el nut to a torque of 5 N•m–6 N•m.