MAINS POWER SUPPLY

F
Carry out the following operations with the power
supply disconnected.
Connect the Phase (L) and Neutral (N) to the 230 V~
power supply.
The board has a F5 A fuse on the Phase.
Connect the earth of the electrical system to terminal
PE.
E045S

6. START-UP

RISKS
PE N L
1
2 3 4 5 6 7 8
PERSONAL PROTECTIVE EQUIPMENT
MAIN
M1
M2
LAMP
Carry out the following operations (refer to the specific
C
C
sections).
M
M

1. Turn power on to the board.

230
2. Check that the status of the LEDs is correct.
60 W max
230 V~
3. Configure the number of motors (Basic program-
ming,
4. Enable the encoders, if present (Basic program-
ming,
5. Check the leaf movement (Basic programming,
M2
6. Carry out the SETUP procedure that includes the
registration of BUS 2easy that are connected (Basic
programming,
7. Memorise the radio controls, if used.
8. Complete the required programming.
9. Carry out the final checks to make sure that the
automation system is working correctly with all
the devices installed.
6.1 TURN POWER ON TO THE BOARD
Turn on the mains power supply; the 5 V and 24 V LEDs
come on and the following appears on the display:
bo
, then the FW version (e.g.
required).
If the SETUP has already been carried out
on the display and then the automation status (e.g.
For LED and display signals see § Diagnostics.
11
+
-
F
/R1
/R2
9 10 11
15 16 17 18
V~
Mn
).
En
).
M1
,
).
tL
).
2EASY
USB-A
20 21
"
24 V
3 W max
4.0
S0
), then
(SETUP
bo
, appears
00
)
532373 - Rev.A

Advertisement

Table of Contents
loading

Table of Contents